Risk health summary example
Given these scales for likelihood, impact, and overall risk:
And these mitigating controls:
We end up with:
What it looks like written out
Refer to the above screenshots.
Finding the residual likelihood
Inherent likelihood = 8
Sum of likelihood mitigation = 60%
Residual likelihood = 8 x (100% - 80%) = 3.2 (Moderate)
Finding the residual impact
Inherent impact = 8
Sum of impact mitigation = 80%
Residual impact = 8 x (100% - 80%) = 1.6 (Low)
Finding the overall mitigation
Inherent risk = 8 x 8 = 64 (High)
Residual risk = 3.2 x 1.6 = 5.12 (Low)
Overall mitigation = (64 - 5.12) / 64 = 92%